Consolidation Completed

GEO installed a consolidation monitoring system at this site in California and relayed all measurements to a secure Quickview website.

Keller used a combination of deep dynamic compaction and wick drains to densify and consolidate the soil at the site. The site is now ready for construction of a large warehouse facility.

 

Consolidation completed
AMTS monitored consolidation

This AMTS monitored settlement plates that were distributed across the site. Piezometers, tiltmeters, and vibration monitors were also deployed.

 

Settlement contour plot from Quickview

Quickview used data from settlement plates, shown as yellow diamonds, to generate a settlement contour plots: red shows the least settlement, blue shows the most. The same view also showed current readings for piezometers, tiltmeters, and vibration monitors.